Pool renovation

April 1, 2021

The swimming pool has had new pipes and skimmers installed and has been pressure tested. A new plinth laid, and a replacement pump house is almost complete. Electrical works have begun and are progressing well. The pool surround paving brickwork is in the process of being restored and this is likely to be completed within a couple of weeks. The fibreglass works are underway but have been delayed due to poor weather conditions. The planned date of completion is the 1st of May weather permitting. The pool is still to be refilled, the water treated, and the system tested.